Hall bathroom
Before any changes
Cabinet and toilet removed, shower doors gone, the three medicine cabinets
are all gone, too. We also took down the window curtains. See
the toilet in its new home in the master bathroom.
Day two
Alison inspects the new hardware for the bathtub. The new bathtub
faucet is already installed!
Day seven
Now things are getting serious in here - the floor and subfloor are
gone. That's the Earth you see below.
Day eight
Now they're rebuilding the subfloor (it had water damage and needed
to be replaced). They were using the master
bedroom to cut these planks the right size.
Day ten
The subfloor is all done now.
And the new medicine cabinet body is in! But no door yet.
The fixtures are starting to pop out of the wall, and the hole is starting
to close up. There's also a drink cup in the toothbrush holder.
Day thirteen
This is after the first pass of bathtub refinishing. They apparently
spray ceramic onto it somehow.
Day fourteen
You can see the tiles that are going to go in the hole where the old
shower control used to be.
Day
twenty
We lived here a week before we had a bathroom we could take a shower
in. This is still
a couple of nights before we finally got this bathroom finished.
Day
Twenty-nine
Woo! Compare this to the original picture
of this bathroom.
Day
Thirty-one